  1. What is being bought, for how much, and what happens next.
  2. Next step tells you the procedure and where the notice is; Watch to follow deadlines and the award.
  3. Full scope, exact values, dates and bidders open with this market's edition, with a calendar export.

Coos Bay Rail Line 15 Bridge Rehabilitation

Coos Bay Rail Line bridge rehabilitation - 15 bridge structures on the 134-mile shortline, including all three swing spans, the Vaughn Viaduct and the Coal Bank Slough bridge

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Oregon International Port of Coos Bay
Where
Oregon · Coos Bay
Segments
Civil works, Track
Technology areas
Track & civil
Status
In execution — Complete: the Port lists Rail Bridge Rehabilitation among its completed Coos Bay Rail Line projects.
Value band
$25–100m
Currency
USD
Key dates (month)
Build grant received December 2018

Status in full

Read more

Complete: the Port lists Rail Bridge Rehabilitation among its completed Coos Bay Rail Line projects. It was funded by an award from the US Department of Transportation's Better Utilizing Investments to Leverage Development programme, received in December 2018, with matching funds pledged by the State of Oregon. The Port names no contractor for the work.

Next step

In execution — awarded and under way.

Read the notice: Oregon International Port of Coos Bay ↗

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (2)
  • Published bidders

Full detail withheld: 5 fields. In the United States edition · See a fully open example

3 sources · all primary
  • ● Oregon International Port of Coos Bay · Coos Bay Rail Line Bridge Rehabilitation — the Port's own project page. States an award of $20 million from the Better Utilizing Investments to Leverage Development grant programme to support rehabilitation of 15 bridge structures along the Coos Bay Rail Line, and that the line is a 134-mile shortline railroad running through Coos, Douglas and Lane Counties traversing 121 bridges between the Eugene interchange and end of line at Coquille, many built when the line was constructed in 1914-1916. Read 14 September 2026, HTTP 200. (published 2026 · checked 2026-09-14)
  • ● Oregon International Port of Coos Bay · Coos Bay Rail Line Projects — the Port's own project list. Read 14 September 2026, HTTP 200: Rail Bridge Rehabilitation (completed), the Port Infrastructure and Development Program comprehensive tie and ballast replacement project (completed), the Coos Bay Rail Line tunnel rehabilitation project (completed), the CBRL timber bridge rehabilitation project (completed) and the Coos Bay swing span bridge project (completed). (published 2026 · checked 2026-09-14)
  • ● Oregon International Port of Coos Bay · Coos Bay Swing Span Bridge Project (Completed), dated 31 May 2019. Read 14 September 2026, HTTP 200. Records that two centre support columns failed in mid-April 2018 rendering the bridge inoperable, that the Port set up a transload facility on the North Spit within two weeks, and that the repairs replaced the centre structural columns and bracing and repaired the electrical mechanical system. States that future capital improvements to the 100-year-old bridge 'will be part of the bridge rehabilitation project made possible by the federal Better Utilizing Investments to Leverage Development grant the Port received in December of 2018'. Publishes no value for the emergency repair. (published 2019-05-31 · checked 2026-09-14)

Related tenders

Same buyer first, then the same segment in this market.

Show all 6 related tenders

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.