A Better Red MAX Red Line Extension Hillsboro

A Better Red: MAX Red Line extension and reliability improvements - ten more stations to Hillsboro, double-tracking at Gateway and the airport, and a new Gateway North station

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Tri-County Metropolitan Transportation District of Oregon (TriMet)
Where
Oregon · Beaverton
Segments
Track, Civil works, Stations & depots, Rolling stock
Technology areas
Track & civil, Rolling-stock hardware
Status
In execution — Complete: the project opened in August 2024 on TriMet's own project history page.
Value band
$100–500m
Currency
USD
Key dates (month)
Construction 2021–20 · Service opened August 2024

Status in full

Read more

Complete: the project opened in August 2024 on TriMet's own project history page. It extended MAX Red Line service west from Beaverton Transit Center to a new terminus at the Hillsboro Airport/Fairgrounds station, serving ten more existing Blue Line stations, doubled MAX service between Beaverton and Hillsboro, built TriMet's first new MAX station in nine years at Gateway North, converted two single-track sections - the Red Line at Gateway Transit Center and at the Portland International Airport station - to double track, and built two new bridges and pathways. The FY2027 capital programme still carries funding on the Red Line Extension and Reliability Improvements line, PRJ_4638, and the budget's operating-impacts table books a yearly increase net of estimated new fare revenue.

Next step

In execution — awarded and under way.

Read the notice: TriMet (Tri-County Metropolitan Transportation District of Oregon) ↗

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (2)
  • Published bidders
  • Note on the figure

Full detail withheld: 6 fields. In the United States edition · See a fully open example

5 sources · all primary
  • ● TriMet (Tri-County Metropolitan Transportation District of Oregon) · MAX Red Line Extension (A Better Red) — TriMet's own project history page. Read 14 September 2026, HTTP 200. States the opening date of 28 August 2024, ten additional stations, construction 2021-2024, and a cost of $215 million including six new light rail vehicles. (published 2026 · checked 2026-09-14)
  • ● TriMet (Tri-County Metropolitan Transportation District of Oregon) · Resolution No. 25-04-17 authorizing a modification of the construction project management services contract with Shiels Obletz Johnsen for the MAX Red Line Extension and Reliability Improvements Project, 23 April 2025 (PDF, 4 pages, 212,849 bytes). (published 2025-04-23 · checked 2026-09-14)
  • ● TriMet (Tri-County Metropolitan Transportation District of Oregon) · Resolution No. 26-01-02 authorizing a contract modification with Siemens Mobility, Inc. to use contract options to purchase up to 56 light rail vehicles, 28 January 2026 (PDF, 3 pages, 219,983 bytes). (published 2026-01-28 · checked 2026-09-14)
  • ● TriMet (Tri-County Metropolitan Transportation District of Oregon) · FY2027 Adopted Budget (PDF, 402 pages, 33,714,353 bytes). Sections used: the Capital Improvement Program (pages 343-367) with the adopted CIP funding detail by project, the five-year CIP forecast and the CIP impacts on operations; the FY2025 transportation statistics (page 16); and the Maintenance Division's FY2026 accomplishments (page 209). (published 2026-05-27 · checked 2026-09-14)
  • ● TriMet (Tri-County Metropolitan Transportation District of Oregon) · Making Transit Better: MAX Improvements — TriMet's own list of completed and current light rail improvement projects, including the NE 82nd Ave MAX Improvements Project and the August 2020 Steel Bridge track, switch and signal replacement (8,680 feet of rail, lift joints, expansion rails and two switch sections). Read 14 September 2026, HTTP 200. (published 2026 · checked 2026-09-14)

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
Track Rehabilitation Project MAX System Five-yearTriMetAwarded$5–25mPublished May 2026
Type 6 Light Rail Vehicles Siemens Mobility S700TriMetIn execution$500m–1bn
Light Rail Vehicle Fleet Replacement and ExpansionTriMetPlanned$25–100mSanctioned May 2026
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Type 1 Traction Power Substation MAX Blue LineTriMetIn execution$25–100m
Pioneer Courthouse Square Type 1 Traction Power SubstationTriMetIn execution$5–25m
Type 1 Substation Replacement MAX FY2027 ProgrammeTriMetPlanned$5–25mSanctioned May 2026