Electrical connections traction substations stage III
Eesti Raudtee — electrical connections for the new traction substations, stage III: awarded to Elektrilevi OÜ on two lots, with a third lot closed without a winner
Awarded to Elektrilevi — Aktsiaselts Eesti Raudtee now holds 2 positions with this supplier.
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the European Union edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Aktsiaselts Eesti Raudtee
- Where
- Estonia · Tartu
- Segments
- Electrification
- Status
- In execution — Contract award notice 762411-2023 of December 2023, buyer reference 273485.
- Value band
- $5–25m
- Currency
- EUR
- Key dates (month)
- Published December 2023 · Awarded December 2023
Status in full
Read more
Contract award notice 762411-2023 of December 2023, buyer reference 273485. The notice carries three result lots: LOT-0001 and LOT-0002 awarded to Elektrilevi OÜ with contracts concluded in December 2023, and LOT-0003 carrying TenderResultCode clos-nw with the non-award justification code chan-need, a decision of the buyer because of a change in needs. The buyer's own reason for the third lot is carried here so that the outcome is not left to inference. Lot attribution is read from the parallel arrays tender-lot-identifier, result-lot-identifier and BT-13714-Tender. One tender was received on each of the two awarded lots; the notice publishes no submission statistics for the lot that closed without a winner.
Next step
Recorded award: Elektrilevi — Electrical connections traction substations stage III — Elektrilevi OÜ
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (2)
- Published bidders
Full detail withheld: 5 fields. In the European Union edition · See a fully open example
2 sources · all primary
- ● Tenders Electronic Daily (TED) · Contract award notice 762411-2023, 15 December 2023 — Elektrifitseerimise projekti uute veoalajaamade elektrilised liitumised III, buyer reference 273485, EUR 15,067,403.18 to Elektrilevi OÜ across LOT-0001 at EUR 8,490,211.18 and LOT-0002 at EUR 6,577,192.00, with LOT-0003 carrying clos-nw and the non-award justification chan-need (published 2023 · checked 2026-09-13)
- ● EU Vocabularies (Publications Office) · Non-award justification authority table — ins-fund 'Decision of the buyer, because of insufficient funds', all-rej 'All tenders, requests to participate or projects were withdrawn or found inadmissible', other (published 2026 · checked 2026-09-13)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Eesti Raudtee CCS modules Tapa Narva | Eesti Raudtee | Open | no value published on the notice | Closes October 2026 |
| Eesti Raudtee Aegviidu Tapa Tartu electrification | Eesti Raudtee | In execution | $100–500m | Awarded February 2023 |
| Eesti Raudtee CCS systems six sections fifty stations | Eesti Raudtee | In execution | $100–500m | Awarded November 2020 |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Eesti Raudtee Tapa Narva contact line | Eesti Raudtee | In execution | $25–100m | Awarded December 2024 |
| Eesti Raudtee Lagedi Aegviidu contact line | Eesti Raudtee | In execution | $25–100m | Awarded March 2024 |
| Eesti Raudtee Kaarepere Tartu curve straightening | Eesti Raudtee | In execution | $5–25m | Awarded January 2024 |
Browse: the Atlas · European Union · players · events
Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.