Electrical connections Jõgeva Tapa Tartu stage II
Eesti Raudtee — electrical connections for the Jõgeva, Tapa and Tartu traction substations, stage II: awarded to Elektrilevi OÜ across three lots
Awarded to Elektrilevi — Aktsiaselts Eesti Raudtee now holds 2 positions with this supplier.
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the European Union edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Aktsiaselts Eesti Raudtee
- Where
- Estonia · Tapa
- Segments
- Electrification
- Status
- In execution — Contract award notice 86413-2023 of February 2023, buyer reference 259564.
- Value band
- $5–25m
- Currency
- EUR
- Key dates (month)
- Awarded January 2023
Status in full
Read more
Contract award notice 86413-2023 of February 2023, buyer reference 259564. The notice predates eForms and the TED Search API exposes no winner; the lots and holders were read from the Estonian procurement register's own open-data copy of the February 2023 award notices, which attributes each lot separately: lot 1 Jõgeva veoalajaam on contract 16308, lot 2 Tapa veoalajaam on contract 16307 and lot 3 Tartu veoalajaam on contract 16323, all three to Elektrilevi OÜ, with contracts concluded in January 2023 and one tender received on each lot. The register's three award blocks are printed in the order lot 3, lot 2, lot 1, each carrying its own lot number, so every value here is read from the lot number its own block names and not from the block's position. The notice states a works period of at most 1,190 days for Jõgeva, 1,010 days for Tapa and 1,250 days for Tartu from the first instalment reaching Elektrilevi OÜ.
Next step
Recorded award: Elektrilevi — Electrical connections Jõgeva Tapa Tartu stage II — Elektrilevi OÜ
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (1)
- Published bidders
Full detail withheld: 5 fields. In the European Union edition · See a fully open example
2 sources · all primary
- ● Tenders Electronic Daily (TED) · Contract award notice 86413-2023, 10 February 2023 — Elektrifitseerimise projekti uute veoalajaamade elektrilised liitumised II, buyer reference 259564, EUR 14,970,646.82 to Elektrilevi OÜ across three lots — Jõgeva veoalajaam EUR 4,874,435.39, Tapa veoalajaam EUR 4,714,851.73 and Tartu veoalajaam EUR 5,381,359.70 (published 2023 · checked 2026-09-13)
- ● Republic of Estonia — Riigihangete register · Open-data interface, contract award notices by month: GET https://riigihanked.riik.ee/rhr/api/public/v1/opendata/notice_award/<YYYY>/month/<M>/xml — the route through which this file read the winners of pre-eForms Estonian award notices (published 2026 · checked 2026-09-13)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Eesti Raudtee CCS modules Tapa Narva | Eesti Raudtee | Open | no value published on the notice | Closes October 2026 |
| Eesti Raudtee Aegviidu Tapa Tartu electrification | Eesti Raudtee | In execution | $100–500m | Awarded February 2023 |
| Eesti Raudtee CCS systems six sections fifty stations | Eesti Raudtee | In execution | $100–500m | Awarded November 2020 |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Eesti Raudtee Tapa Narva contact line | Eesti Raudtee | In execution | $25–100m | Awarded December 2024 |
| Eesti Raudtee Lagedi Aegviidu contact line | Eesti Raudtee | In execution | $25–100m | Awarded March 2024 |
| Eesti Raudtee Kaarepere Tartu curve straightening | Eesti Raudtee | In execution | $5–25m | Awarded January 2024 |