BBT Brenner base tunnel, 55 km, railway equipment
BBT SE — Brenner base tunnel (55 km): civil works 96% excavated; railway-equipment packages next
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the European Union edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Galleria di Base del Brennero – Brenner Basistunnel BBT SE
- Where
- Austria · Innsbruck
- Segments
- Civil works, Track, Signalling, Electrification, Telecoms
- Technology areas
- Track & civil, Signalling & train control, Digital operations, Cybersecurity
- Status
- In execution — Excavation about 96% complete (221 of 230 km); commissioning date of 2032 under review — BBT SE to present an updated construction programme in 2026
- Value band
- over $1bn
- Currency
- EUR
- Key dates (month)
- Founded December 2004 · Cost forecast May 2023 · Programme update 2026 · Commissioning 2032
Next step
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (4)
- Published bidders
- Note on the figure
Full detail withheld: 6 fields. In the European Union edition · See a fully open example
6 sources · 5 primary
- ● Galleria di Base del Brennero – Brenner Basistunnel BBT SE · Project progress (km excavated, lots) (published 2026 · checked 2026-09-11)
- ● Galleria di Base del Brennero – Brenner Basistunnel BBT SE · Nach Genehmigung der Prognose für die Gesamtprojektkosten Refinanzierungsanträge gestellt (newsroom) (published 2023-05-02 · checked 2026-09-11)
- ● Galleria di Base del Brennero – Brenner Basistunnel BBT SE · Project overview (55 km tunnel, 64 km with Inn valley tunnel) (published 2026 · checked 2026-09-11)
- ○ Südtirol News · BBT-Betrieb 2032 wird in Frage gestellt — Bauprogramm-Aktualisierung (published 2026-03-10 · checked 2026-09-11)
- ● Parlament Österreich — Parlamentskorrespondenz · Verkehrsminister legt aktualisierten ÖBB-Rahmenplan 2027-2032 für Ausbau des Schienennetzes vor (PK0614) (published 2026-06-24 · checked 2026-09-11)
- ● Bundesministerium für Innovation, Mobilität und Infrastruktur (BMIMI) · Bundesregierung beschließt ÖBB-Rahmenplan 2027–2032 (press release) (published 2026-06-17 · checked 2026-09-11)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| DB InfraGO permanent-way repair framework, four waves · 3 parts | DB InfraGO | Open | over $1bn each part (USD) | Closes November 2026 |
| DB InfraGO permanent-way repair frameworks wave 1 | DB InfraGO | Open | €1.41bn framework maximum | |
| DB InfraGO permanent-way repair frameworks wave 2 | DB InfraGO | Open | over $1bn | Closes November 2026 |
| DB InfraGO permanent-way repair frameworks wave 3 | DB InfraGO | Open | over $1bn | Closes November 2026 |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| DB InfraGO permanent-way repair frameworks wave 4 | DB InfraGO | Open | over $1bn | Closes December 2026 |
| LTG Infra Rail Baltica Kaunas–Panevėžys formation structures | LTG Infra | Open | over $1bn | Closes October 2027 |
| Ligne Nouvelle Montpellier–Perpignan construction Phase 1 | SNCF Réseau | Open | over $1bn | Closes October 2026 |
Browse: the Atlas · European Union · players · events
Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.