Tender · In execution
? How to use this page

How to use a tender page

  1. What is being bought, for how much, and what happens next.
  2. Next step tells you the procedure and where the notice is; Watch to follow deadlines and the award.
  3. Full scope, exact values, dates and bidders open with this market's edition, with a calendar export.

Franconia-Springfield Bypass

Franconia-Springfield Bypass — a grade-separated flyover taking passenger trains over the freight main line

Awarded to Dragados — Virginia Passenger Rail Authority now holds 2 positions with this supplier.

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Virginia Passenger Rail Authority
Where
Virginia · Alexandria
Segments
Civil works, Track, Signalling
Technology areas
Track & civil, Signalling & train control
Status
In execution — Construction, estimated completion 2029.
Value band
$500m–1bn
Currency
USD
Key dates (month)
Cmgc solicitation issued August 2023 · Cmgc awarded December 2023 · Cm solicitation issued October 2024 · Cm awarded May 2025 · Estimated completion 2029

Status in full

Read more

Construction, estimated completion 2029. The Executive Director's Report of August 2026 records retaining wall construction, fibre-optic utility relocations and test pitting for jack-and-bore drainage installation, with two test drilled shafts built and load testing under way. VPRA states that the delay anticipated from the Kinder Morgan gas pipeline relocation is approximately twelve months. All eleven right-of-way acquisitions are complete: every condemnation has been filed and the voluntary acquisitions have closed.

Next step

In execution — awarded and under way.

Read the notice: Virginia Passenger Rail Authority (VPRA) ↗

Recorded award: Dragados — Franconia-Springfield Bypass CM/GC contract, as part of the Flatiron-Herzog Joint Venture

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (5)
  • Published bidders
  • Note on the figure

Full detail withheld: 6 fields. In the United States edition · See a fully open example

7 sources · all primary
  • ● Virginia Passenger Rail Authority (VPRA) · Notice of Award, RFP 01-007-23-0001 — CM/GC Contractor for the Franconia-Springfield Bypass Project, awarded 6 December 2023 (published 2023-12-06 · checked 2026-09-14)
  • ● Virginia Passenger Rail Authority (VPRA) · Notice of Award, RFP 01-007-24-0002 — Construction Management Services in support of the Franconia-Springfield Bypass project, awarded 30 May 2025 (published 2025-05-30 · checked 2026-09-14)
  • ● Virginia Passenger Rail Authority (VPRA) Board · Resolution of 27 August 2026: FY27 Budget Amendment and Approval of Management Reserve Balance, with Exhibit A, the Amended Fiscal Year 2027 Budget (I-95 Corridor comparison and capital project tables) (published 2026-08-27 · checked 2026-09-14)
  • ● Virginia Passenger Rail Authority (VPRA) · Executive Director's Report, August 2026 — project-by-project cost, contractor, status and grant tables (61 pages) (published 2026-08-27 · checked 2026-09-14)
  • ● Virginia Passenger Rail Authority (VPRA) · Project Updates — staff presentation to the Board, 27 August 2026 (right-of-way acquisition, utility relocations, Franconia to Lorton and Siding A procurement schedules) (published 2026-08-27 · checked 2026-09-14)
  • ● Virginia Passenger Rail Authority (VPRA) · FY27 VPRA Capital Budget — staff presentation to the Board, 22 January 2026 (capital budget changes, financial plan, management reserve) (published 2026-01-22 · checked 2026-09-14)
  • ● Virginia Passenger Rail Authority (VPRA) · Board Meeting Materials — agendas, minutes, decision briefs, resolutions and staff presentations, August 2026 back to January 2026 (published 2026-09 · checked 2026-09-14)

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
Long Bridge project, north and south packages · 2 partsVPRAIn executionVaries by part
Long Bridge North PackageVPRAIn executionover $1bnAwarded December 2023
Long Bridge South PackageVPRAIn execution$500m–1bnAwarded January 2025
Alexandria Fourth TrackVPRAIn execution$100–500mCompletion 2027
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Fairfax County sewer relocation Franconia LortonVPRABids closed$5–25mBids closed August 2026 · award expected
Franconia to Lorton Third TrackVPRAPlannedno contract value published
Railroad Bridges over Newington RoadVPRAPlannedno contract value publishedTarget 2029

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.