Nebraska Central four rail sidings

Four new rail sidings on the Norfolk, Ord and Stromsburg subdivisions of the Nebraska Central line

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Nebraska Central Railroad Company
Where
Nebraska · Norfolk
Segments
Track
Technology areas
Track & civil
Status
In execution — The grant period ends 31 October 2026, so completion or an extension is due.
Value band
$5–25m
Currency
USD
Key dates (month)
Signed March 2024 · Period end October 2026

Next step

Awarded March 2024 — in execution.

Read the notice: USAspending award 69A36524420300CRSNE ↗

Recorded award: Nebraska Central Railroad — FRA grant for four rail sidings (signed 6 March 2024)

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (2)
  • Published bidders
  • Note on the figure

Full detail withheld: 6 fields. In the United States edition · See a fully open example

1 source · primary
  • ● USAspending award 69A36524420300CRSNE · FRA grant to Nebraska Central Railroad Company for four rail sidings; federal $6,317,982 with non-federal $4,390,462; signed 6 March 2024; performance to 31 October 2026; track leased from Union Pacific (published 2024-03-18 · checked 2026-10-08)

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
Ashmont and Mattapan Infrastructure UpgradesMBTAOpen$100–500m
Light Rail Modernization Program Tranche 3 Cromwell FacilityMDOT MTAOpenestimated cost class L: over $100 million, in MTA's own construction look-ahead of August 2026; MTA publishes no contract valuePublished July 2026
Nebraska Central infrastructure improvementsNebraska Central RailroadIn execution$5–25mAwarded May 2020
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Red Line Hi-Rail Access Tunnel AlewifeMBTAOpen$25–100m
Light Rail Metro Facilities Ancillary maintenance constructionMDOT MTAOpenestimated cost class H: $15 million to $30 million, for the matching line in MTA's own on-call master contract look-ahead of August 2026; MTA publishes no contract value
CTA Red Line Extension 120th Street yard shopCTAOpenover $20m projected (CTA Buying Plan projection, not an award)Closes October 2026

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.