Port Bienville classification yard
Classification yard and intermodal switch lead at Port Bienville Industrial Park for the port's short-line railroad
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Hancock County Port & Harbor Commission (Port Bienville Railroad)
- Where
- Mississippi · Kiln
- Segments
- Track, Civil works
- Technology areas
- Track & civil
- Status
- In execution — Engineering and environmental work first; the commission planned construction to begin in 2026.
- Value band
- $5–25m
- Currency
- USD
- Key dates (month)
- Commission release March 2024 · Fra agreement signed June 2025 · Period start June 2025 · Period end August 2028 · Planned construction start 2026
Next step
Recorded award: HCPHC — Federal grant for the Port Bienville classification yard (signed June 2025)
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (5)
- Published bidders
- Note on the figure
Full detail withheld: 6 fields. In the United States edition · See a fully open example
4 sources · all primary
- ● USAspending: FRA award 69A36525420130CCDMS to Hancock County Port & Harbor Commission (Port Bienville rail yard) · Award record, assistance listing 20.325: $7,320,000 federal, no non-federal funding recorded, signed 11 June 2025, period 1 June 2025 to 30 August 2028; scope an eight-track classification yard and a 3,500-linear-foot intermodal switch lead at Port Bienville Industrial Park, Hancock County, with capacity for 235 railcars (published 2025-06-23 · checked 2026-10-08)
- ● Hancock County Port & Harbor Commission - release: $7.32 million for Port Bienville Intermodal Expansion Phase I (26 March 2024) · Commission release (posted on its site 19 July 2024): FY24 appropriations funding from USDOT; total project budget $25.4 million in two phases, Phase 1 $14.6 million for a seven-track classification yard adding 220 railcar spaces and Phase 2 $10.8 million for a truck-to-rail intermodal facility; Phase 1 fully funded with earlier RESTORE Act and MDOT multimodal awards totalling $3.7 million; construction planned for 2026; Port Bienville Short Line Railroad is a Class III line owned by the Commission and interchanging with CSX five days a week (published 2024-03-26 · checked 2026-10-08)
- ● USAspending: MARAD Port Infrastructure Development award 693JF72245014 to Hancock County Port & Harbor Commission · Award record, assistance listing 20.823: $4,140,000 federal, non-federal $2,857,981.78, total $6,997,981.78, signed 22 August 2023, period to 1 January 2029; new rail storage yard of about 130 spaces with two sets of storage tracks and a siding at the port; below the US$5 million floor on its own (published 2025-10-17 · checked 2026-10-08)
- ● Hancock County Port & Harbor Commission - news and blog index · Newsroom index read on 8 October 2026: latest posts concern a new airport tenant, a rail safety award, a GOMESA dock award and a $1 million SMIF grant for Facility 2 at Port Bienville; no rail procurement notice listed (published 2026 · checked 2026-10-08)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Ashmont and Mattapan Infrastructure Upgrades | MBTA | Open | $100–500m | |
| Light Rail Modernization Program Tranche 3 Cromwell Facility | MDOT MTA | Open | estimated cost class L: over $100 million, in MTA's own construction look-ahead of August 2026; MTA publishes no contract value | Published July 2026 |
| Red Line Hi-Rail Access Tunnel Alewife | MBTA | Open | $25–100m |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Light Rail Metro Facilities Ancillary maintenance construction | MDOT MTA | Open | estimated cost class H: $15 million to $30 million, for the matching line in MTA's own on-call master contract look-ahead of August 2026; MTA publishes no contract value | |
| MARC Mechanical Ancillary maintenance construction master contract | MDOT MTA | Open | estimated cost class G: $10 million to $15 million, for the matching line in MTA's own on-call master contract look-ahead of August 2026; MTA publishes no contract value | |
| CTA Red Line Extension 120th Street yard shop | CTA | Open | over $20m projected (CTA Buying Plan projection, not an award) | Closes October 2026 |