NOPB gateway fluidity and capacity yard works
Switch upgrades, yard expansion and automated switching to raise capacity and car storage across three NOPB yards
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- New Orleans Public Belt Railroad (NOPB)
- Where
- Louisiana · New Orleans
- Segments
- Track, Digital operations
- Technology areas
- Track & civil
- Status
- In execution — The federal performance period ended on 31 December 2024.
- Value band
- $5–25m
- Currency
- USD
- Key dates (month)
- Grant announced February 2020 · Federal record signed February 2023 · Period end December 2024 · Claiborne due August 2024
Next step
Recorded award: NOPB / Rail NOLA — CRISI grant 69A36523403760CRSLA, federal, switching and railcar storage capacity, 1 November 2022 to 31 December 2024
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (4)
- Published bidders
- Note on the figure
Full detail withheld: 6 fields. In the United States edition · See a fully open example
3 sources · all primary
- ● USAspending: FRA CRISI grant 69A36523403760CRSLA (NOPB) · Federal award record: $7,297,421 federal, non-federal $10,946,209, total $18,243,630; period 1 November 2022 to 31 December 2024; switching and railcar storage capacity. (published 2023-02-16 · checked 2026-10-07)
- ● Congressional release: $7.3 million for Port of New Orleans rail project · Release of 28 February 2020 hosted on the NOPB site: CRISI grant of about $7.3 million to upgrade switches and expand three regional rail yards for 500 more rail cars. (published 2020-02-28 · checked 2026-10-07)
- ● NOPB release: major infrastructure projects near completion · Release of 5 August 2024: transloading industrial park and Claiborne Yard expansion near completion; $7.29 million CRISI grant for railyard space and automated switching; $3 million transload project funded half by LADOTD. (published 2024-08-05 · checked 2026-10-07)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Ashmont and Mattapan Infrastructure Upgrades | MBTA | Open | $100–500m | |
| Light Rail Modernization Program Tranche 3 Cromwell Facility | MDOT MTA | Open | estimated cost class L: over $100 million, in MTA's own construction look-ahead of August 2026; MTA publishes no contract value | Published July 2026 |
| Red Line Hi-Rail Access Tunnel Alewife | MBTA | Open | $25–100m |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Light Rail Metro Facilities Ancillary maintenance construction | MDOT MTA | Open | estimated cost class H: $15 million to $30 million, for the matching line in MTA's own on-call master contract look-ahead of August 2026; MTA publishes no contract value | |
| CTA Red Line Extension 120th Street yard shop | CTA | Open | over $20m projected (CTA Buying Plan projection, not an award) | Closes October 2026 |
| Valley Metro light rail streetcar operations five-year | Valley Metro | Open | value not published |
Browse: the Atlas · United States · players · events
Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.