Double Track NWI Project One contract
Double Track NWI Project Number 1 - main construction contract for the second track, bridges and overhead power, bid by the Walsh/Herzog joint venture
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Northern Indiana Commuter Transportation District
- Where
- Indiana · Chesterton
- Segments
- Track, Electrification, Rolling stock
- Technology areas
- Track & civil, Predictive maintenance
- Status
- In execution — Complete: Double Track NWI entered service in May 2024; change orders continued into 2025.
- Value band
- $100–500m
- Currency
- USD
- Key dates (month)
- Board award month November 2021 · Change order 18 January 2025 · In service May 2024
Next step
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (3)
- Published bidders
Full detail withheld: 5 fields. In the United States edition · See a fully open example
3 sources · 2 primary
- ○ Rep. Mrvan site - South Shore's double track open for business (reprint) · Secondary: reprint dated 10 June 2024 of a LaPorte County Herald-Dispatch article stating the NICTD board awarded Double Track Project Number 1 to Walsh/Herzog in November 2021 on a bid of $304.8 million; NICTD's own board minutes for that meeting were not read (published 2024-06-10 · checked 2026-10-07)
- ● FHWA Center for Innovative Finance Support - South Shore Line Double Track Project profile · Project profile: total cost, funding stack (CIG, ARP, RRIF, state, RDA, local), design-bid-build, credit agreement 21 December 2022, named contractors (published 2023 · checked 2026-10-07)
- ● NICTD board awards - 27 January 2025 · One-page NICTD results of board awards for the 27 January 2025 meeting: project, amount and awardee as printed (published 2025-01-27 · checked 2026-10-07)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| NICTD traction power substation modernisation | NICTD (South Shore Line) | Open | value not published on the solicitation | Closes November 2026 |
| NICTD 100 Series APS units | NICTD (South Shore Line) | Awarded | $5–25m | Awarded July 2025 |
| West Lake Corridor design-build | NICTD (South Shore Line) | In execution | $500m–1bn |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Double Track NWI second track programme | NICTD (South Shore Line) | In execution | $500m–1bn | |
| Double Track NWI FTA full funding grant | NICTD (South Shore Line) | In execution | $100–500m | Awarded January 2021 |
| West Lake Corridor FTA full funding grant | NICTD (South Shore Line) | In execution | $100–500m | Awarded November 2020 |
Browse: the Atlas · United States · players · events
Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.