NICTD traction power substation modernisation

Traction Power Substation Modernization Project - build one new substation in Porter County and refurbish one in LaPorte County, with options to refurbish five more across Indiana and Cook County, Illinois

Closes November 2026; Northern Indiana Commuter Transportation District has awarded 9 tenders since 2020, Walsh most often.

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Northern Indiana Commuter Transportation District
Where
Indiana · Chesterton
Segments
Electrification, Stations & depots
Status
Open — Bids close on 5 November 2026.
Value band
value not published on the solicitation
Currency
USD
Key dates (month)
Pre bid meeting August 2026 · Bid deadline November 2026 · Latest addendum October 2026 · Design amendment 5 board award January 2026

Status in full

Read more

Bids close on 5 November 2026. NICTD publishes no estimated value; seven addenda had been issued by 2 October 2026.

Next step

Open — closes November 2026.

Read the notice: NICTD Plan Room - Construction jobs for bid ↗

Withheld in the free surface

  • Full scope
  • How the figure was arrived at
  • Key dates (4)
  • Published bidders

Full detail withheld: 4 fields. In the United States edition · See a fully open example

3 sources · all primary

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
NICTD 100 Series APS unitsNICTD (South Shore Line)Awarded$5–25mAwarded July 2025
West Lake Corridor design-buildNICTD (South Shore Line)In execution$500m–1bn
West Lake Corridor FTA full funding grantNICTD (South Shore Line)In execution$100–500mAwarded November 2020
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Double Track NWI second track programmeNICTD (South Shore Line)In execution$500m–1bn
Double Track NWI FTA full funding grantNICTD (South Shore Line)In execution$100–500mAwarded January 2021
NICTD FTA state of good repair grantNICTD (South Shore Line)In execution$25–100mAwarded September 2025

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.