NICTD 100 Series APS units
100 Series auxiliary power supply units for the South Shore Line fleet, awarded to Toshiba International Corporation
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Northern Indiana Commuter Transportation District
- Where
- Indiana · Chesterton
- Segments
- Rolling stock
- Technology areas
- Rolling-stock hardware
- Status
- Awarded — NICTD's board awarded the contract to Toshiba International Corporation on 28 July 2025.
- Value band
- $5–25m
- Currency
- USD
- Key dates (month)
- Board award July 2025
Next step
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (1)
- Published bidders
Full detail withheld: 5 fields. In the United States edition · See a fully open example
2 sources · all primary
- ● NICTD board awards - 28 July 2025 · One-page NICTD results of board awards for the 28 July 2025 meeting: project, amount and awardee as printed (published 2025-07-28 · checked 2026-10-07)
- ● NICTD board awards - 18 May 2026 · One-page NICTD results of board awards for the 18 May 2026 meeting: project, amount and awardee as printed (published 2026-05-18 · checked 2026-10-07)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| NICTD traction power substation modernisation | NICTD (South Shore Line) | Open | value not published on the solicitation | Closes November 2026 |
| West Lake Corridor design-build | NICTD (South Shore Line) | In execution | $500m–1bn | |
| West Lake Corridor FTA full funding grant | NICTD (South Shore Line) | In execution | $100–500m | Awarded November 2020 |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Double Track NWI second track programme | NICTD (South Shore Line) | In execution | $500m–1bn | |
| Double Track NWI FTA full funding grant | NICTD (South Shore Line) | In execution | $100–500m | Awarded January 2021 |
| NICTD FTA state of good repair grant | NICTD (South Shore Line) | In execution | $25–100m | Awarded September 2025 |