Ship Creek Bridge 114.3 Replacement

Replacement of the Ship Creek pony truss and beam spans at MP 114.3 in lower downtown Anchorage with a ballast-deck steel I-beam bridge

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Alaska Railroad Corporation
Where
Alaska · Anchorage
Segments
Civil works, Track
Technology areas
Track & civil
Status
In execution — Bridge replacement began in September 2025; final completion was expected by 31 July 2026.
Value band
$5–25m
Currency
USD
Key dates (month)
Grant signed June 2025 · Construction start September 2025 · Substantial completion planned May 2026 · Final completion planned July 2026 · Grant performance end December 2027

Next step

In execution — awarded and under way.

Read the notice: Alaska Railroad fact sheet: Bridge 114.3 Replacement ↗

Recorded award: Alaska Railroad — State of Good Repair grant, Ship Creek Bridge 114.3 replacement

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (5)
  • Published bidders

Full detail withheld: 5 fields. In the United States edition · See a fully open example

2 sources · all primary
  • ● Alaska Railroad fact sheet: Bridge 114.3 Replacement · Ship Creek bridge replacement: construction from September 2025, substantial completion by 1 May 2026 and final completion expected by 31 July 2026, FTA funded with 20% ARRC match (published 2026-03-17 · checked 2026-10-08)
  • ● USAspending award AK-2025-018 · FTA State of Good Repair grant to Alaska Railroad Corporation for bridge replacement at MP 114.3: federal 12,389,600, non-federal 3,097,400, signed 4 June 2025, performance to 31 December 2027 (published 2025-06-04 · checked 2026-10-08)

Related tenders

Same buyer first, then the same segment in this market.

Show all 6 related tenders

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.