Downingtown Station relocation Keystone Corridor

Downingtown Station relocation, Keystone Corridor — new station half a mile east with four-quadrant parking and a replacement railroad bridge over US 322

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
PennDOT Bureau of Rail, Freight, Ports and Waterways
Where
Pennsylvania · Philadelphia
Segments
Stations & depots, Civil works, Electrification
Technology areas
Track & civil
Status
Planned — Early action work is largely complete: DOWNS interlocking removed, catenary foundations poured, catenary steel structures procured and a structure demolished.
Value band
value not published
Currency
USD
Key dates (month)
Early action complete 2026 · Utility relocation start June 2026 · Utility relocation complete November 2026 · Catenary modifications start July 2026 · Construction start 2027 · Construction complete 2031

Status in full

Read more

Early action work is largely complete: DOWNS interlocking removed, catenary foundations poured, catenary steel structures procured and a structure demolished. Utility relocation began in June 2026 and is anticipated complete in October or November 2026, with overhead catenary modifications by Amtrak forces from July 2026. Construction of the station and the new railroad bridge over SR 322 is anticipated to start in mid-2027 and to be complete in 2031.

Next step

Planned — target 2027.

Read the notice: Pennsylvania Department of Transportation ↗

Withheld in the free surface

  • Full scope
  • How the figure was arrived at
  • Key dates (6)
  • Published bidders

Full detail withheld: 4 fields. In the United States edition · See a fully open example

2 sources · all primary

Related tenders

Same buyer first, then the same segment in this market.

Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Ashmont and Mattapan Infrastructure UpgradesMBTAOpen$100–500m
Paoli-Darby Road project Keystone CorridorPennDOT Rail BureauPlanned$25–100m
PennDOT Rail Freight Transportation Assistance ProgramsPennDOT Rail BureauPlannedno 2026 round award published; PennDOT's State Rail Plan publishes the five preceding rounds at $26.0m to $42.5m a year

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.