Tender · In execution
? How to use this page
How to use a tender page
- What is being bought, for how much, and what happens next.
- Next step tells you the procedure and where the notice is; Watch to follow deadlines and the award.
- Full scope, exact values, dates and bidders open with this market's edition, with a calendar export.
SKOL rehabilitation CRISI grant
South Kansas and Oklahoma Railroad rehabilitation project, FY2019 CRISI grant to KDOT
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- Kansas Department of Transportation, Multimodal Transportation and Innovation
- Where
- Kansas · Cherryvale
- Segments
- Track, Civil works
- Technology areas
- Track & civil
- Status
- In execution — Grant period ends 31 October 2026; completion was not published.
- Value band
- $25–100m
- Currency
- USD
- Key dates (month)
- Agreement signed June 2021 · Period start May 2021 · Period end October 2026 · Record last modified May 2026
Next step
Recorded award: KDOT — CRISI award for the SKOL rehabilitation project (signed June 2021)
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (4)
- Published bidders
- Note on the figure
Full detail withheld: 6 fields. In the United States edition · See a fully open example
1 source · primary
- ● USAspending: CRISI award to KDOT, South Kansas and Oklahoma Railroad Rehabilitation Project · Award 69A36521402770CRSKS, $29,570,583 federal obligation, non-federal funding $13,627,880, total funding $43,198,463, signed 3 June 2021, 1 May 2021 to 31 October 2026 (record last modified 26 May 2026) (published 2021-06-03 · checked 2026-10-08)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Cimarron Valley Railroad CRISI upgrade | KDOT | In execution | $5–25m | |
| Kyle Railroad Concordia rail replacement | KDOT | In execution | $5–25m | |
| Heartland Flyer extension to Newton | KDOT | Planned | $311m to $573m (KDOT capital estimates) |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Ashmont and Mattapan Infrastructure Upgrades | MBTA | Open | $100–500m | |
| Light Rail Modernization Program Tranche 3 Cromwell Facility | MDOT MTA | Open | estimated cost class L: over $100 million, in MTA's own construction look-ahead of August 2026; MTA publishes no contract value | Published July 2026 |
| Red Line Hi-Rail Access Tunnel Alewife | MBTA | Open | $25–100m |
Browse: the Atlas · United States · players · events
Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.