Tender · In execution
? How to use this page

How to use a tender page

  1. What is being bought, for how much, and what happens next.
  2. Next step tells you the procedure and where the notice is; Watch to follow deadlines and the award.
  3. Full scope, exact values, dates and bidders open with this market's edition, with a calendar export.

Traction power substation equipment replacement Wave 1

Traction power substation equipment replacement, Wave 1

Awarded to Cleveland Electric — Metropolitan Atlanta Rapid Transit Authority now holds 2 positions with this supplier.

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Metropolitan Atlanta Rapid Transit Authority
Where
Georgia · Atlanta
Segments
Electrification
Status
In execution — Awarded to Cleveland Electric Company in November 2025, with 'None' recorded in the base-term-with-options column; payments had been recorded against it by June 2026, including spend in fiscal year 2026.
Value band
$25–100m
Currency
USD
Key dates (month)
Awarded November 2025 · Fy26 payments to June 2026

Part of MARTA traction power substation replacement, in waves · 2 parts. Other parts: Traction power substation system replacement.

Status in full

Read more

Awarded to Cleveland Electric Company in November 2025, with 'None' recorded in the base-term-with-options column; payments had been recorded against it by June 2026, including spend in fiscal year 2026. It is the only contract this file cites against any part of the traction power substation replacement programme, whose ten-year budget line is carried separately here.

Next step

Awarded November 2025 — in execution.

Read the notice: Metropolitan Atlanta Rapid Transit Authority ↗

Recorded award: Cleveland Electric — Traction power substation equipment replacement Wave 1 — Cleveland Electric Company

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (2)
  • Published bidders

Full detail withheld: 5 fields. In the United States edition · See a fully open example

2 sources · all primary
  • ● Metropolitan Atlanta Rapid Transit Authority · FY26 MARTOC Annual Report — including the schedule of Payments and Contracts $20,000 or More for 1 July 2025 to 30 June 2026 (vendor, purpose, contract number, award date, base term with options, award amount, paid to date) (published 2026 · checked 2026-09-14)
  • ● Metropolitan Atlanta Rapid Transit Authority · FY2027 Proposed Capital Improvement Program Budget (April 2026), including Attachment A — State of Good Repair proposed projects ten-year forecast FY27–FY36 (PDF pages 19–21, text layer), Attachment B — MARTA City of Atlanta proposed projects ten-year forecast (PDF page 22) and Attachment C — MARTA Clayton County proposed projects ten-year forecast (PDF page 23); Attachments B and C carry no text layer and were read as pixels rendered at 300 dpi on 14 September 2026 (published 2026-04 · checked 2026-09-14)

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
CQ400 heavy rail car procurementMARTAIn execution$500m–1bnAwarded November 2019
Communications-Based Train ControlMARTAIn execution$500m–1bnAwarded December 2024
Better Breeze Automated Fare Collection SystemMARTAIn execution$100–500mAwarded January 2024
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Station Rehabilitation Program construction managementMARTAIn execution$100–500mAwarded March 2020
Station Rehabilitation Program architectural engineering designMARTAIn execution$25–100mAwarded February 2020
Direct Fixation Rail Fastener ReplacementMARTAIn execution$25–100mAwarded June 2026

Browse: the Atlas · United States · players · events