LA Metro Southeast Gateway Line preconstruction

LA Metro — Southeast Gateway Line: 14.5-mile light rail from Slauson to Pioneer, advanced works let as construction manager/general contractor with a preconstruction budget

Awarded to Herzog — Los Angeles County Metropolitan Transportation Authority now holds 1 position with this supplier.

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Los Angeles County Metropolitan Transportation Authority
Where
California · Los Angeles
Segments
Civil works, Track, Stations & depots, Electrification, Signalling, Rolling stock
Technology areas
Track & civil, Signalling & train control, Rolling-stock hardware
Status
In execution — Advanced Works CM/GC Phase 1 awarded to Flatiron-Herzog, a SGL Joint Venture, on the Board’s consent calendar February 2025; preconstruction is under way and Metro is conducting underground utility investigations in South Gate to support future engineering design.
Value band
over $1bn
Currency
USD
Key dates (month)
Lpa approved February 2024 · Eir eis certified April 2024 · Record of decision August 2024 · Cmgc matter introduced January 2025 · Board award February 2025 · Assumed opening year 2036

Status in full

Read more

Advanced Works CM/GC Phase 1 awarded to Flatiron-Herzog, a SGL Joint Venture, on the Board’s consent calendar February 2025; preconstruction is under way and Metro is conducting underground utility investigations in South Gate to support future engineering design. No competitive tender is open for the main build, and that is the delivery model rather than a pause: under construction manager/general contractor the contractor is already on board and prices the construction phases by negotiation with Metro inside the authorised preconstruction budget.

Next step

Awarded February 2025 — in execution.

Read the notice: Los Angeles County Metropolitan Transportation Authority — Legistar legislative record ↗

Recorded award: Herzog — Southeast Gateway Line Advanced Works CM/GC Phase 1 — awarded to Flatiron-Herzog, a SGL Joint Venture, of which Herzog is one of the two partners (Contract PS119518000, 27 February 2025)

Withheld in the free surface

  • Full scope
  • Exact value
  • How the figure was arrived at
  • Key dates (6)
  • Published bidders
  • Note on the figure

Full detail withheld: 6 fields. In the United States edition · See a fully open example

4 sources · all primary

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
LA Metro East San Fernando Valley Light RailLA MetroAwardedover $1bnAwarded September 2026
LA Metro D Line Extension Section 1LA MetroIn executionvalue not published for the programme total
LA Metro Sepulveda driverless heavy railLA MetroPlannedover $1bn
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
LA Metro A and E Line Interlock RailWorksLA MetroBids closed$25–100m
LA Metro K Line Extension Torrance HillLA MetroAwarded$25–100mAwarded March 2026
LA Metro C Line traction power substationsLA MetroPlanned$100–500m

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.