Valley Line West LRT Marigold Infrastructure Partners
Valley Line West LRT — 14 street-level stops, 2 elevated stations, 2 bridges and 2 facilities on the 27 km Valley Line (Marigold Infrastructure Partners, design-build-partial-finance)
Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the Canada edition — one edition is free with one email. Open your free edition · Open this record in the Atlas
- Buyer
- City of Edmonton — LRT Expansion
- Where
- Alberta · Edmonton
- Segments
- Track, Civil works, Stations & depots, Electrification
- Technology areas
- Track & civil, Digital operations
- Status
- In execution — 68.7% complete as measured by the independent certifier at the end of Q2 2026; construction anticipated complete in 2028, followed by testing and commissioning
- Value band
- over $1bn
- Currency
- CAD
- Key dates (month)
- Construction start 2021 · Progress 68 7pc June 2026 · Construction complete 2028
Next step
Withheld in the free surface
- Full scope
- Exact value
- How the figure was arrived at
- Key dates (3)
- Published bidders
Full detail withheld: 5 fields. In the Canada edition · See a fully open example
3 sources · all primary
- ● City of Edmonton · Valley Line West LRT (project page) (published 2026 · checked 2026-09-12)
- ● City of Edmonton · Valley Line West LRT — Quarterly Progress Report, Q2 2026 (published 2026 · checked 2026-09-12)
- ● Government of Alberta · Public transit initiatives (Valley Line West provincial share) (published 2026 · checked 2026-09-12)
Related tenders
Same buyer first, then the same segment in this market.
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Capital Line South Extension Phase 1 | City of Edmonton | In execution | $500m–1bn | Completion 2029 |
| Metro Line Northwest Extension Phase 1 | City of Edmonton | In execution | $100–500m | |
| Valley Line West 46 light rail vehicles | City of Edmonton | In execution | value not published |
Show all 6 related tenders
| Tender | Buyer | Status | Value band | Next key date |
|---|---|---|---|---|
| Green Line Phase 1 Maintenance Storage Facility | City of Calgary | Open | value not published | Closes November 2026 |
| High-floor LRV supply three bidders shortlisted | City of Edmonton | Awarded | value not published | |
| Valley Line Southeast Downtown Mill Woods | City of Edmonton | In execution | value not published by the City |
Browse: the Atlas · Canada · players · events