CTA Red Line Extension 95th to 130th Street

CTA Red Line Extension mainline design-build, contract C22FT102829986 — 5.5 miles from 95th Street to 130th Street, four stations and a new yard — to Walsh VINCI Transit Community Partners

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Chicago Transit Authority
Where
Illinois · Chicago
Segments
Track, Civil works, Stations & depots, Signalling, Electrification
Technology areas
Track & civil, Signalling & train control
Status
In execution — Ground broken at the future Michigan Avenue station in April 2026; station construction begins in 2027 and the extension is to be in service in 2030.
Value band
contract value not published
Currency
USD
Key dates (month)
RFQ issued 2022 · RFP issued 2023 · Ffga signed January 2025 · Federal funding paused October 2025 · Lawsuit filed March 2026 · Temporary restraining order March 2026 · Funding restored March 2026 · Groundbreaking April 2026 · Station construction starts 2027 · In service 2030

Status in full

Read more

Ground broken at the future Michigan Avenue station in April 2026; station construction begins in 2027 and the extension is to be in service in 2030. Federal reimbursement was suspended from October 2025 and restored in March 2026 under a court order.

Next step

In execution — awarded and under way.

Read the notice: Chicago Transit Authority ↗

Recorded award: CTA — Full Funding Grant Agreement of 10 January 2025 pledging of Capital Investment Grant funds for the Red Line Extension, and of Major Capital Investment Grant funding for RPM Phase One and RLE

Withheld in the free surface

  • Full scope
  • How the figure was arrived at
  • Key dates (10)
  • Published bidders
  • Note on the figure
  • Exact value

Full detail withheld: 6 fields. In the United States edition · See a fully open example

6 sources · all primary
  • ● Chicago Transit Authority · CTA Celebrates Start of the Historic Red Line Extension Project by Breaking Ground at the Future Michigan Avenue Station (published 2026-04-24 · checked 2026-09-13)
  • ● Chicago Transit Authority · FY2026 Budget Book (President's 2026 Budget Recommendations; FY2026-2030 Capital Improvement Program) (published 2025-10 · checked 2026-09-13)
  • ● Chicago Transit Authority · Committee on Finance, Audit and Budget — agenda, 11 March 2026 (purchase and sales award recommendations) (published 2026-03-11 · checked 2026-09-13)
  • ● Chicago Transit Authority · Chicago Transit Authority Sues Federal Government Over Paused Red Line Extension and Red & Purple Modernization Project Funding (published 2026-03-20 · checked 2026-09-13)
  • ● Chicago Transit Authority · Red Line Extension (RLE) and Red & Purple Modernization Project Funds Unfrozen (published 2026-03-27 · checked 2026-09-13)
  • ● Chicago Transit Authority · Red Line Extension Project (published 2026 · checked 2026-09-13)

Related tenders

Same buyer first, then the same segment in this market.

Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
CTA Red Line Extension 120th Street yard shopCTAOpenover $20m projected (CTA Buying Plan projection, not an award)Closes October 2026
CTA 7000-Series railcars CRRC Sifang AmericaCTAIn execution$500m–1bn
CTA Red Line Extension parking facility constructionCTAPlannedover $20m projected (CTA Buying Plan projection, not an award)

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.