Dillingham Utility Relocation (CCUR IV)

Relocation of water, sewer, electric, fuel, communications and drainage utilities along Dillingham Boulevard in Kalihi-Palama ahead of the guideway

Every fact on this page is free. Exact values, dates, award detail and the procurement route open in the United States edition — one edition is free with one email. Open your free edition · Open this record in the Atlas

Buyer
Honolulu Authority for Rapid Transportation
Where
Hawaii · Honolulu
Segments
Civil works
Technology areas
Track & civil
Status
In execution — Utility relocation along Dillingham Boulevard is due complete by the end of 2026.
Value band
just under $500m (HART) · $100–500m (USD, for comparison)
Currency
USD
Key dates (month)
Award announced August 2022 · Notice to proceed October 2022 · Construction start planned January 2023 · Completion planned 2022 January 2026 · Completion stated 2026 2026

Next step

Awarded August 2022 — in execution.

Read the notice: HART release: Dillingham utility relocation awarded, 18 Aug 2022 ↗

Withheld in the free surface

  • Full scope
  • How the figure was arrived at
  • Key dates (5)
  • Published bidders

Full detail withheld: 4 fields. In the United States edition · See a fully open example

5 sources · all primary
  • ● HART release: Dillingham utility relocation awarded, 18 Aug 2022 · HART news release: Dillingham Boulevard utility relocation contract awarded to Nan, Inc., valued at just under $500m, bid about 3% below the independent cost estimate (published 2022-08-18 · checked 2026-10-08)
  • ● HART release: downtown utility relocation complete, 21 Jul 2026 · HART news release: downtown utility relocation under CCUR III complete; $217.8m contract awarded May 2022; Dillingham Boulevard utility work due complete by end of 2026 (published 2026-07-21 · checked 2026-10-08)
  • ● HART Rail FAQs · HART FAQ: HART oversees design and construction, the City's Department of Transportation Services oversees operations and maintenance; Segments 1 and 2 open; Segment 3 under construction for 2030 completion and 2031 service; extension to Ala Moana unfunded (published undated · checked 2026-10-08)
  • ● HART The Project page · HART project page: Skyline is 18.9 miles and 19 stations East Kapolei to Civic Center under the 2022 Recovery Plan; milestone timeline from 2005 to April 2026; FFGA and Recovery Plan documents linked (published undated · checked 2026-10-08)
  • ● USAspending award HI-2024-013 · FTA formula grant to City and County of Honolulu, $20m with $5m non-federal, for third-party utility relocation ahead of the Segment 3 contractor, period 12 Sep 2024 to 30 Jun 2027 (published 2024-09-12 · checked 2026-10-08)

Related tenders

Same buyer first, then the same segment in this market.

TenderBuyerStatusValue bandNext key date
Segment 3 Extension Design, Ala MoanaHARTAwarded$25–100m
City Center Guideway and Stations (Segment 3)HARTIn executionover $1bnAwarded August 2024
Skyline Core Systems and Operations ContractHARTIn executionover $1bnAwarded March 2011
Show all 6 related tenders
TenderBuyerStatusValue bandNext key date
Honolulu Rail Transit Full Funding Grant AgreementHARTIn executionover $1bn
Downtown Utility Relocation (CCUR III)HARTIn execution$100–500mAwarded May 2022
Station and Park-and-Ride Construction PackagesHARTPlanned$500m–1bn

Browse: the Atlas · United States · players · events

Compiled by Watchtower to editorial standards the Managing Partner sets and enforces. Public record only — every datum carries its source.